Northern Grampians Shire Council is protesting against plans by GWMWater to charge for the installation of fire hydrants and tanks on the new pipeline project.
Council representatives met in Horsham earlier this month with staff from GWMWater and the Country Fire Authority, to discuss implications for council and the shire as a whole in regard to the closure of the channel system when the Wimmera Mallee Pipeline is completed.
General Manager Customer Services, Jim Nolan, reported that the installation of new fire hydrants and storage tanks along the pipeline route in the shire had been a major issue.
He said with the cessation of channel flows, the new system would provide fire hydrants on all pipelines. The design has been to generally have a hydrant or tank outlet at about five kilometre intervals, to ensure a good coverage of the serviced area.
Mr Nolan said for Northern Grampians Shire, this would involve 21 hydrants and 42 tanks.
``The original estimate provided was that the infrastructure works would cost around $115,000. Now the estimate is between $300,000 and $400,000. The final cost will only be known after every site is individually assessed,'' he said.
Mr Nolan said the State Government had allocated $115,000 for the works, but this was only payable after council agreed to sign a legal agreement that requires it to pay for all installation and maintenance costs.
Since discussions had taken place with GWMWater, council officers had moved to identify priority locations for between 10 and 15 tank sites using available trust funds.
This would at least give some additional fire security to the affected areas of the shire.
It was recommended that the priority installations be proceeded with and that council agree to signing an amended agreement for the provision of the hydrants and tanks, only to the extent of the available GWMWater trust funds allocated and as long as council is not committed to the installation of all works at its cost.
Council will also lobby the CFA, State and Federal Governments to see if additional funds could be made available for the remaining parts of the project.
Applications will also be made for any additional funding that may be available under existing funding programs such as the CFA Fire Access Subsidy Scheme.
Cr Dorothy Patton said the demands that were being put on council to cover installation costs was cause for alarm.
``The concern I have is that GWMWater asked for a recommendation from the CFA, they got that and now they are pulling back from that recommendation. They are saying it is council's responsibility to cover installation costs,'' Cr Patton said.
Cr Wayne Rice said he was disappointed the costings for installation were not factored into the costs when construction of the pipeline commenced.
``I wonder why it wasn't factored in during the planning stages. It certainly should have been,'' he said.
``This whole thing smells of incompetence and I am very disappointed. When you close channels up that fire trucks could back up to, water has to come from somewhere else and someone should have looked at this.
``We work very hard to balance our budget to provide the best we can to our communities and I want to send a clear message to the people who came up with this, that this council simply does not have the money.
``All this should have been worked out at the start, not wait until now and tell councils they need to come up with the money. My message to them is our answer is no.''